Home/Blog/WEATHERING GUIDANCE

WEATHERING GUIDANCE

Minimum 150mm rooflight upstand guidance

Why a rooflight kerb is commonly raised at least 150mm above the finished roof surface and where project advice is required.

THE SHORT ANSWER

For many UK flat-roof details, the rooflight upstand is designed to finish at least 150mm above the completed roof covering at its lowest point. This helps protect the opening from standing water, snow, splashback and blocked drainage.

Measure from the finished roof

The height is measured from the completed waterproofing or roof finish—not from the structural deck. Insulation, screed, falls, paving and green-roof build-ups can all change the final level.

A nominal 150mm timber kerb installed before the roof build-up may therefore be too low once insulation and waterproofing are added.

Falls and thresholds

On a tapered or sloping roof, check the lowest exposed point around the complete perimeter. Terraces, paving and green roofs need careful coordination because their finished surfaces may sit above the membrane.

Any reduced-height or flush detail needs project-specific design and agreement from the relevant designer, waterproofing provider and building-control team.

Project checklist

01Set the height from the finished roof level
02Check the lowest side of the kerb
03Include insulation and falls in the calculation
04Coordinate terraces and green-roof finishes
05Do not reduce the height without project approval
Important guidance note

This is general UK detailing guidance, not approval for a particular roof. Always check the current specification, waterproofing warranty and project requirements.

OG
PREPARED BY
Overhead Glazing Technical Team

Bespoke rooflight specification, project coordination and installation across London and the UK.

PROJECT-SPECIFIC ADVICE

Send us your plans
before you build.

We can review the rooflight type, opening, glass, access and typical detail for your project.